Airport Housing Project(Enabling And Infrastructure Works)
Project Location :
 
Jeddah, Kingdom of Saudi Arabia.
Client:
 
Ministry of Housing
Consultant:
 
Saudi Arabian Parsons Ltd. (SAPL)
Contract Value:
 
338 Million SR , 90 Million USD
Project Start:
 
September, 2013
Project Completion:
 
August, 2015
The project as an approximate area of 2,000,000 m2. FSA scope of work are enabling works, MEP utilities, road works and landscaping. It will be completed 600 days from site handover.
 
>> Click on the image to view more project photos
Riyadh Metro Project
Project Location :
 
Riyadh, Kingdom of Saudi Arabia.
Client:
 
Arriyadh Development Authority
Consultant:
 
RAMPED (Louis Berger / Hill International - JV)
Contract Value:
 
29,325 Million SR , 7,820 Million USD
Project Start:
 
October, 2013
Project Completion
 
September, 2018
The Riyadh Metro project is the largest metro project in the region. It is divided in to three (3) packages and Package 3 was awarded to FAST Riyadh Metro Alliance. The FAST Riyadh Metro Alliance is a consortium comprising multi-national groups known in their respective field of expertise.
Construction :
 
FCC (Leader), Samsung C&T, Strukton and Freyssinet Saudi Arabia.
Rolling Stock and railway providers :
 
Alstom
Designers :
 
Atkins, Typsa and Setec Group
Package 3 is comprised of Lines 4,5 and 6. It has an estimated length of 12.9km for the underground and 58.7km for elevated viaducts with 25 no. of stations.
 
>> Click on the image to view more project photos
The Headquarters Business Park Project
Location:
 
Jeddah, Kingdom of Saudi Arabia
Client:
 
Adeem Al Wataniah for Construction and Development
Consultant:
 
Saudi Diyar
Contract Value:
 
827 Million SR , 220 Million USD
Project Start:
 
July, 2008
Project Completion
 
February, 2015
This project located on the Jeddah Corniche consists of the West Tower that consists of 56 floors rising 250m from the ground level and an East Tower consisting of 17 floors and a central podium consisting of 8 floors for parking space for a total built up area of 165,000m².

The building will be used as office space with state of the art smart systems pre-installed.
 
>> Click on the image to view more project photos
Jet Propulsion Center
Location:
 
Jeddah, Kingdom of Saudi Arabia
Client:
 
Saudia Aerospace Engineering Industries
Consultant:
 
Ghafari Associates
Contract Value:
 
470 Million SR , 125 Million USD
Project Start:
 
January, 2013
Project Completion
 
May, 2016
The project consists of the construction of the Jet Propulsion Center of an Engine Maintenance Auxiliary Power Unit facility located within the King Abdul Aziz International.

The building is made of reinforced concrete sub-structure, its super structure is of structural steel framing. External walls are made of precast concrete panels while its roof cover adopts the use of standing seam metal roofing system. The Facility has a mezzanine floor, a court yard with a uniquely designed mosque and an attached three level administrative offices. The external development includes utilities, ground paving and landscaping, guard houses, ground parking cover, retaining walls, perimeter fence and gates.
 
>> Click on the image to view more project photos
Atturaif Development Project - Phase I & II
Location:
 
Riyadh, Kingdom of Saudi Arabia
Client:
 
Arriyadh Development Authority (ADA)
Consultant:
 
Buro Happold
Contract Value:
 
394 Million SR , 105 Million USD
Project Start:
 
May, 2011
Project Completion
 
April, 2015
This project for Arriyadh Development Authority (ADA) includes the restoration of Atturaif ruins where Palaces and other important buildings of the first Saudi State were located almost 200 years ago in-line with its objective to create a world class public destination of culture, education and tourist functions.

FSA scope of work includes the Lifestyle Museum, Horse Museum, Military Museum, Public Space, External Work and Restoration & Conservation Works covering a total land area of around 64,000 m².
 
>> Click on the image to view more project photos
Haramain High-Speed Rail Airport East Interchange HHR-AEI
Location:
 
Jeddah, Kingdom of Saudi Arabia
Client:
 
SAUDI RAILWAYS ORGANIZATION
Consultant:
 
DAR AL HANDASAH SHAIR AND PARTNERS
Main Contractor:
 
AL RAJHI ALLIANCE
Contract Value:
 
490 Million SR , 130 Million USD
Project Start:
 
July, 2012
Project Completion
 
December, 2015
The project is primarily divided to two (2) major components: road bridges constituting Airport East Interchange and Haramain High Speed Rail Links connecting the railway track to airport stations (HHR).

There are four (4) different structures constituting the Airport East Interchange under the scope of Freyssinet SA namely AP2, AP3, AP9 and AP10.

AP2, AP3 and AP10 are road bridges composed of abutments, piers and precast deck whereas AP9 is an underpass that provides access from the North to the Ring Road Express Way.

The high speed rail under Freyssinet SA scope comprises 2 links connecting the airport to Madinah at the North (link #1) and to Makkah at the South (link #2). Each one of the 2 links is constituted of 2 lines A & B for entrance to & exit from the airport. The total length of the links is 4,965m. The structure of the links is composed of segmental precast deck supported by piers with a height up to 16m. Deep & shallow foundations constitute the substructure. Long spans up to 110m are executed in balanced cantilever technique.

All decks for road & railway bridges are in prestressed concrete, as per post-tension technique.
 
>> Click on the image to view more project photos
PSM/BCM Viaducts (Riyadh Metro)
Location:
 
Riyadh, Kingdom of Saudi Arabia
Consultant:
 
RAMPED (Louis Berger / Hill International - JV)
Contract Value:
 
319 Million SR , 85 Million USD
Project Start:
 
November, 2014
Project Completion
 
October, 2016
This project comprises of the viaducts construction using the PSM (precast segmental method) and BCM (balanced cantilever method) for the Riyadh Metro project package "3". The Lines included in this contract are Lines (4) and (6), each line consists of two elevated bridges "viaducts".
>> Click on the image to view more project photos
Park & Ride Projects
Location:
 
Riyadh, Kingdom of Saudi Arabia
Client:
 
ArRiyadh Development Authority (ADA)
Consultant:
 
R A M P E D (Louis Berger / Hill International - JV)
Contract Value:
 
255.63 Million SR , 68.168 Million USD
Project Start:
 
October, 2015
Project Completion
 
May, 2018 (Ongoing)
Park and Ride Facilities are Located in close proximity to a number of Stations in the Riyadh Metro System. P4.3: Along University Road in front of the service entrance of Princess Nora University next to elevated Station 4E1. P6.2: Intersection of King Abdullah Road & Sheikh Hassan Bin Hussein Bin Ali St. next to elevated station 6F1 P6.4: At the crossing of Abdulrahman Ibn Awf & Prince Saad bin Abdulrahman St next to underground station 6G1.
>> Click on the image to view more project photos
Riyadh Metro Depot (Line 4/6)
Location:
 
Riyadh, Kingdom of Saudi Arabia
Client:
 
ArRiyadh Development Authority (ADA)
Consultant:
 
R A M P E D (Louis Berger / Hill International - JV)
Contract Value:
 
55.125 Million SR , 14.7 Million USD
Project Start:
 
November, 2015
Project Completion
 
May, 2016 (Ongoing)
Depot Facilities are located next to line 4 Metro Railway, the buildings in this project are: Stabling Area, Manual Washing Area, Wayside Area, Workshop Area, Energy Building, Car Park Area, Administration Building, Automatic Washing Plant. The main purpose of this building is to serve the trains of the Metro regarding (maintenance, parking, cleaning And checking) and also to control and monitor all the systems for Riyadh Metro Project.
 
 
|
|
|
|
|
|
|
Copyright 2017 FREYSSINET SAUDI ARABIA CO. LTD. All rights reserved. | Developed By CSS-PROVIDERS  |  Designed By PIVIART